2010年P(guān)MP美國項目管理考試習題及答案28
QUEST Which is not one of the five classifications of work found in a purchasing operafion?
A Management
B Buying
C Follow-up and expediting
D Marketing
E Clerical
參考答案:D
QUEST _____ is based on information gathered and analyzed about demand and supply. This forecast provides a prediction of short and long term prices and the underlying reasons for those trends.
A Demand forecast
B Price forecast
C Supply forecast
D Production forecast
E None of the above.
參考答案:B
QUEST Fixed-price and incentive-type contracts place responsibility for performance and financial risks associated with delay or non-performance on the:
A Buyer
B Third party
C Contractor
D All of the above
E None of the above
參考答案:C
QUEST The _____ specification delineates specific measurable capabilities or parameters for which a product can be tested as part of the acceptance procedure.
A Performance
B Functional
C Technical
D Base Line
E None of the above.
參考答案:A

QUEST There are four methods of government procurement. Which is not one of these methods?
A Assistance
B Sealed bidding
C Competitive proposals
D Acquisition
E Small purchases
參考答案:D
相關(guān)試題:
2010年P(guān)MP美國項目管理考試習題及答案27
試題推薦:
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選1
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選2
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選3