QUEST 100 % inspection of output is:
A the best proven method to ensure quality
B is expensive, ineffective approach to quality management
C can never be, justified
D can still leave some defects undetected
E B and D only
參考答案:E
QUEST Quality control charts show a characteristic of the product or service against:
A the specification limits
B customer requirements
C control limits based on three standard deviations in each direction
D control limits based on six standard deviations in each direction
E A and D only
參考答案:C
QUEST Variables quality data are:
A quantitative or qualitative data
B quality data for which the product or service is designed and built
C reflect measurements on a continuous scale of a characteristic of the produce or service.
D Indicate management's understanding of the concept of variability
E B and C only
參考答案:E
QUEST Attributes quality data are:
A quantitative or qualitative data
B quality data for which the products or services is designed and built.
C reflect measurements on a continuous scale of a characteristic of the product or service
D indicate management's understanding of the concept of variability
E A and B only
參考答案:E
QUEST Which of the following are among Phil Crosby's "absolutes of quality'.
A the performance of standard is zero defects
B do everything right the first time, each time
C constantly improve each product and each service
D the measurement system is the cost of nonconformance
E A and D only
參考答案:E