2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案八十六
QUEST The major difference between project and line management is that the project manager may not have any control over which basic management function?
A Decision-making
B Staffing
C Rewarding
D Tracking/monitoring
E Reviewing
參考答案:B
QUEST A good team leader must be concerned not only with _____ but also with _____ .
A Long term goals; short term goals
B Organizational goals; personal goals
C Legitimate power; referent power
D Group efficiency; power and authority
E Tasks to be accomplished; needs of the team members
參考答案:E
QUEST In small companies, project managers and line managers are:
A Never the same person
B Always the same person
C Sometimes the same person
D Always in disagreement with each other
E Forced to act as their own sponsors
參考答案:C
QUEST A project manager who allows the team to make the majority of the decisions is demonstrating a(n) ____ leadership style.
A Laissez-faire
B Boss-centered
C Subordinate centered
D Autocratic
E Demographic
參考答案:C
.jpg)
QUEST R & D project managers in high-tech companies most often motivate using _____ power.
A Expert
B Reward
C Referent
D Identification
E None of the above
參考答案:A
相關(guān)試題:
2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案八十五
試題推薦:
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
本站推薦
- 1高速公路項(xiàng)目部2010年度業(yè)務(wù)代表述職報(bào)告
- 2廣西六欽高速某標(biāo)段2010年度施工進(jìn)度計(jì)劃
- 3貴新高速公路粗苯泄漏的應(yīng)急監(jiān)測
- 4交通部試驗(yàn)檢測師:交通安全設(shè)施測試題(2010年度)
- 5交通部試驗(yàn)檢測工程師:橋涵工程試驗(yàn)檢測試題(2010年度)
- 62010年公路工程試驗(yàn)檢測師考試復(fù)習(xí)資料
- 7交通部試驗(yàn)檢測師:公路、材料測試題(2010年度)
- 82010年一級建造師考試模擬題及復(fù)習(xí)大綱
- 92010年全國一級建造師執(zhí)業(yè)資格考試模擬試題(含答案)